ATA-003 / LİKİTGAZ AYDIN – EFELER FACILITIES, Fire System Modernization Project

AYDIN / TURKEY

  • Date: Apr-2021 / Ongoing
  • Customer: LİKİTGAZ

Details

  • Provision of whole project materials such as 
    1. Concrete, re-bar, Anchors
    2. Field erected tanks annular and roof plates and accessories,
    3. Fire Pump building structural steel and cladding,
    4. CS and GS Pipes, fittings, and accessories,
    5. HDPE pipes, fittings, adaptors etc.
    6. Fire Protection devices like deluge valves, hydrants, safety showers, hose reels, sprinklers,
    7. Electrical supply such as Boards, cables, lighting and earthing materials,
  • Civil work scope,
    1. Jet Grout works for a fire water tank and fire pump building.
    2. Excavation and backfilling works. 
    3. Preparation of tank, building and pipe support foundations. 
    4. Installation of Structural steel.
  • Mechanical installation scope,
    1. 900 m3 field erected tank installation with accessories,
    2. Electrical and diesel fire pumps installation with fuel tanks.
    3. Above ground CS & GS, underground HDPE piping installation,
  • Electrical installation scope
  1. Earthing system installation
  2. Power cable pulling, termination,
  3. Lighting systems.
  • Testing and Commissioning of system